Luisa Living construction timeline
From the building permit to moving in: the key milestones of the project in Munich West. Construction started in July 2023 and was completed in December 2024.
01 · Dec 2022
Building permit granted
The Munich building authority grants the permit for the plot at Sigererstraße 12, acquired in February 2021.
02 · Feb 2023
Demolition of the old building
The old detached house makes way for the new build.
03 · July 2023
Start of construction: excavation and base slab
The excavation is secured with sheet piling and the roughly 45 cm thick reinforced-concrete base slab is cast.
04 · Sept 2023
Underground garage and basement
The shared basement with underground garage is built as a watertight concrete structure.
05 · April 2024
Shell and roof completed
Both buildings are structurally complete and the roofs are covered with integrated photovoltaic modules.
06 · July 2024
Façade completed
Façades with rustication, pilasters and a continuous cornice give the urban villas their character.
07 · Sept 2024
Interior fit-out
Floors, kitchens and building services are installed – the top-floor flats reveal their exposed timber beams.
08 · Dec 2024
Outdoor areas completed
Turf, planting and terraces are finished – the complex is ready for occupancy.
09 · Dec 2024
Completion and move-in
Just over two years after the building permit, Luisa Living is complete. All 11 flats are occupied and DEKRA has certified the KfW 40 standard.
The full construction diary with every intermediate step is available on the project website (in German): luisa-living.de/baufortschritt →